So the footings are poured for the 2nd 1/2 of house!
An over view look of the footings for the 2nd floor and garage above
There is still a mound of dirt to move out of there before the
next step-not sure how they get it out!
This is the plumbing rough in for the bathroom and laundry room of
the 2nd floor
So these are the plumbers putting in the radon venting and
roughing in the plumbing shown above!
The men have put in the iron posts to support beams that will be coming
Now you can see all 3 posts. The beams will form a T on top of these posts
to support the garage above. Pictures in future will make more sense
The gravel is laid for the pour of cement to form the slab of floor for the back 1/2 of the
2nd floor which is the rec room, 3 bedrooms and a bath/laundry room
No comments:
Post a Comment